In July 2023, Diamond Key International Group successfully completed yet another Factory Acceptance Test (FAT) for the Vapour Recovery Unit (VRU) in our manufacturing facility located in Yue Yang with technical representatives from the Tsing Yi Terminal, located in Hong Kong SAR.

This project aims to upgrade and retrofit the existing VRU to meet the customer’s requirements, with an objective to build a higher-capacity VRU with improved emission standards while utilising the existing foundation of the original VRU. DKI along with Cool Sorption, designed and manufactured a VRU and control system using the Depot Series DS-710 model, a standardised system for small to medium-sized terminals, commonly used in truck loading areas.

Project Deliverables:
🔹The skid-mounted system's electrical design met IECEx and ATEX explosion-proof certification.
🔹The pneumatic control valve air supply was upgraded from Polyethylene (PE) to stainless steel piping for improved corrosion resistance, tailored to marine climate conditions.
🔹All valves were modified from European standard to ASME-standard.
🔹Two independent metering pipelines were added to the original design, integrated with DKI's latest FlexLinc BC system, featuring a VRU return oil interface.
🔹The new VRU control interface was integrated with DKI’s Terminal Automation System (TAS) for seamless data sharing and management.

Key Customer Benefits:
🔹Cost savings and revenue - Recovering vapour as reusable fuel reduces waste and maintenance costs through efficient rotary vacuum pumps.
🔹Safety assurance - The certified explosion-proof design (IECEx/ATEX) and stress-tested durability (ASME/CAESAR) effectively eliminate explosion risks.
🔹Sustainability leadership - Exceeds global emission standards and reduces pollution.
🔹Tailored solutions - Custom modular designs (compliant with customer's DEPs) with corrosion-resistant upgrades for marine environments.
🔹Smart efficiency tracking - Dual metering lines and the FlexLinc BC interface automatically calculate VOC recovery rates, reducing manual oversight.

IMG_0147

An experienced project manager strategically oversaw each phase, ensuring clear goals, well-defined responsibilities, and adherence to the SMART principle, with continuous tracking to keep the project on schedule. Our goal is to ensure customer satisfaction and mutual success through teamwork. It was an honour to support the customer’s modernisation efforts by providing a complete vapour recovery system solution. This achievement reflects our commitment to collaboration, driving progress towards a more sustainable future.

Leave a Comment

Australia - Head Office

110 Henderson Rd
P.o.Box 2813
Rowville, Victoria 3178
AUSTRALIA
Telephone: +61 3 9730 8888

Malaysia Office

23, Jalan PJU 3/46
Sunway Damansara
47810 Petaling Jaya, Selangor
MALAYSIA
Telephone: +60 3  7496 9238

China Office

Rm 808 Block D JiaHua Building
No 9, 3rd Street ShangDi
HaiDian District
Beijing, China 100085
T: +86 10 6297 1803 / 7663 / 7650

Thailand Office

Suite 403, 4th Floor Tonson Bldg.
50 Soi Tonson,
Ploenchit Road, Patumwan,
Bangkok, Thailand
T: +66 2 652 2617